Flooring shall be replaced along the full length of wall and painting of the surrounding wall to provide a uniform clean finished border, at a minimum. Coordinate with all trades.
Coordinate cabinet modifications as required to accommodate new units. Appearance shall have a clean finished look. Select units to fit within existing space where possible.
Existing exterior louver re-use is strongly preferred, unless too close to grade (and will allow infiltration of snow / rain). Coordinate with exterior scope as required.
Reuse of main hydronic piping is preferred unless deemed in need of replacement. Units to have new local piping and valving, including control valves.
New Unit Ventilators are to include a new local temperature sensor and BACnet compatibility for connection to existing or new BAS.