Introduction
The FY2027 budget for Chicago Public Schools (CPS) includes a capital budget totaling $600.4 million of investments that will focus on priority facilities needs at neighborhood schools, mechanical systems that control the indoor environment and air quality of our schools, building envelope improvements for roofing systems, ADA accessibility, restroom modernizations, student recreation and athletic improvements, site improvements, and continued expansion of technology upgrades and other academic priorities. To support schools throughout the city, the FY2027 capital plan provides funding in five main areas: critical facility needs, interior improvements, programmatic investments, site improvements, and IT upgrades.
CPS will continue to invest in energy efficiency measures, including the replacement of existing equipment with energy-efficient equipment, replacement of steam heating systems with hydronic systems, lighting controls, replacement or addition of Building Automation Systems (BAS) for more efficient systems operations, heat pumps, replacement of existing roof-mounted equipment with energy-efficient equipment, improved roof reflectance and energy efficiency resulting from a water and airtight roofing envelope system, which we can build on to further invest in energy savings through clean energy investments.
CPS is committed to promoting equitable access to high-quality school environments, and equity served as the foundation for the FY2027 capital plan. The District's Equity Office played an important role in developing the FY2027 capital proposal by ensuring that resources are distributed fairly and equitably across CPS schools, allowing all students to share in the District's record-setting progress. In addition, the FY2027 capital budget planning process included several enhancements, most notably around transparency and community outreach.
Community feedback requested more transparency in the prioritization process for Capital projects. In April, CPS held three virtual and two in-person meetings to engage communities in discussing capital priorities for the FY27 capital plan. These sessions, led by the CPS Capital Department, Office of Equity, and Office of Family and Community Engagement (FACE), offered insights into the capital planning process and helped prioritize critical needs. We received over 6,600 survey responses during the capital plan development process. The high number of critical facility needs identified by the Educational Facilities Master Plan (EFMP) is reflected in the proposed Capital budget, which allocates funds across various categories.
The CPS facility portfolio includes 527 campuses and 799 buildings. Our average facility age is over 86 years old, and the total CPS immediate critical facility need is nearly $4 billion. Since FY2017, CPS has invested over $3 billion in capital improvements across the District. These projects include major renovations to ensure our schools remain warm and dry, facility construction to relieve overcrowding, security cameras to provide a safer environment for our children, and renovations to aid programmatic enhancements, among others. Additionally, CPS is continuing to invest in ADA upgrades to ensure all CPS campuses are more accessible.
We have several buildings that are underutilized and a few overcrowded buildings. Based on public feedback, space efficiency is a budget category that was first introduced in the FY25 capital plan and is also proposed in the FY27 capital plan. The Capital team will continue to develop deep dives into the buildings’ portfolio to (a) Determine if there are sections of a building that can be closed off to reduce operational costs, (b) Determine if there are obsolete buildings that should be demolished or replaced, and (c) Determine if there are campuses that are overcrowded with no other solutions other than a capital investment to relieve the overcrowding. Public feedback to the EFMP acknowledged the underutilized and overcrowded buildings, and this budget category will continue the detailed analysis and implement projects to address these challenges as part of a long-term plan.
CPS will continue to incorporate sustainable materials into capital projects, as CPS specifications have been modified to include these materials (examples include energy-efficient mechanical equipment, roofs with higher R-values, low-volatile organic compounds content paint, etc.). We are also seeking public feedback on innovative ways for CPS to share our buildings to support the community.
The FY2027 capital budget is primarily funded by future issuance of general obligation bonds, which are principally repaid by Evidence-Based Funding (EBF). (For more information, please see the Debt Management chapter of the budget book.) A portion of the FY2027 budget is also funded by Tax Increment Financing (TIF) funds, state funding, and other outside resources as they are identified.
Full details on the FY2027 capital budget are available on the interactive capital plan website: www.cps.edu/capitalplanbi. The site allows users to quickly select projects by school, geographic area, type, and year.
CPS’ capital plan aligns with the priorities outlined in the Educational Facilities Master Plan. Future projects will be determined by equity, assessed need, educational priorities, and available funding, with the goal of maximizing the number of students impacted by the capital investments.
District Opportunity Index to Prioritize Investments
In recent years, the District has focused on prioritizing investments that promote equitable access to high-quality learning environments. To advance this work, the District will utilize the Opportunity Index, a tool to help identify opportunity differences, allowing resources to be prioritized for the schools in greatest need. The Opportunity Index was also central to developing this year’s capital plan.
Outside Funding
CPS has a significant backlog of deferred critical facility needs, so additional funding is always being pursued to help mitigate some of this backlog. One of these outside funding sources is the Tax Increment Financing (TIF) funds, which are approved in a variety of categories. Also, CPS continues to work with the State to leverage funding from the Illinois Department of Commerce and Economic Opportunity (DCEO).
Utilizing the $75.6 million in outside funding, CPS is planning capital facility upgrades, programmatic upgrades, and site improvements, in addition to the ITS upgrades at several campuses.
Priority Facility Needs
Every student deserves access to a neighborhood school that is warm, safe, and dry. In addition to the $75.6 million in outside funding, CPS is allocating $375.6 million for critical maintenance projects and interior improvements. As part of our commitment to equity, the District is prioritizing renovations throughout the city to ensure all students can learn and grow in school buildings that support high-quality learning environments.
The FY2027 capital budget addresses the District’s priority renovation projects and most urgent facility needs. We will invest in 18 major roof and envelope projects and 17 renovations to mechanical systems. Along with these projects, the funding will provide:
- $191.6 million for priority roof, envelope, and mechanical projects;
- $80 million for unanticipated emergency repairs;
- $43.6 million for space efficiency and interior improvements;
- $5 million for fire alarm system replacement;
- $10 million for energy efficiency projects.
Support for Students with Physical Limitations
CPS will invest $6 million to increase Americans with Disabilities Act accessibility in 9 schools as part of a multi-year program to ensure all CPS buildings have first-floor accessibility.
Programmatic Investments to Build Upon School Success
CPS is investing $25.3 million in programmatic investments, including pre-k renovations, nutrition and food service improvements, and student recreation and athletic resources. This investment continues the District’s stadium and swimming pool refurbishment program.
Site Improvements that Foster Learning
This year’s capital budget includes $23.5 million to design and build new playgrounds, playlots, and schoolyards across the city so that students can benefit from a well-rounded education that promotes healthy and active development. This includes continuation of the Space to Grow program, which includes investments by the Department of Water Management (DWM) and Metropolitan Water Reclamation District (MWRD). In addition, $26.4 million will be allocated to improve parking lots and replace turf fields.
IT, Facility, and Building System Investments
In FY2027, we are also continuing our multi-year investment in the Technology Modernization Program and high-speed internet for schools throughout the city. In FY2027, the District is allocating $65 million to upgrade school network infrastructure to address equitable connectivity, replace aging hardware at schools, and upgrade our data warehouse and data backups.
Finally, to support cleanliness at every school, $5.5 million will be used to fund the insourcing of custodial equipment.
Five-Year Capital Plan
CPS’ five-year capital plan will include further investments in deferred maintenance, targeted site improvements, and emergency projects. Future projects will be determined by assessed need, district educational priorities, and an equitable distribution of available funding. CPS intends to target annual capital funding of approximately $550 million as part of its five-year capital investment strategy.
|
Budget Category |
FY2028 Budget |
FY2029 Budget |
FY2030 Budget |
FY2031 Budget |
|---|---|---|---|---|
|
Facility Needs |
$355.0 |
$355.0 |
$355.0 |
$355.0 |
|
Interior Improvements |
$10.0 |
$10.0 |
$10.0 |
$10.0 |
|
Programmatic Investments |
$120.0 |
$120.0 |
$120.0 |
$120.0 |
|
IT and Other Investments |
$12.0 |
$12.0 |
$12.0 |
$12.0 |
|
Site Improvements |
$30.0 |
$30.0 |
$30.0 |
$30.0 |
|
Capital Project Support Services |
$23.0 |
$23.0 |
$23.0 |
$23.0 |
|
Total Capital Plan |
$550.0 |
$550.0 |
$550.0 |
$550.0 |
Public Hearings on Proposed FY2027 Capital Plan
Wednesday, July 22, 2026
Capital Plan Hearing
Hearing time: 12:00PM – 1:30PM
CPS staff, families, and community members are invited to attend this virtual hearing regarding the District's 2027 fiscal year Capital Plan.
Where: Members of the public can view this hearing via our YouTube channel during the time listed above at youtube.com/chipubschools
Advanced online registration to speak opens Wednesday, July 15, 2026 at 5:00 pm and will close on Friday, July 17, 2026 at 5:00 pm or after all 30 speaking slots are filled.
Advance registration during this period is available by the following methods:
• Online: Registration Form (recommended)
• Phone: 773-553-1190
Members of the public may submit written comments related to the FY27 Proposed Capital Plan via the form below. The public comment form will remain open from Wednesday, July 15, 2026 at 5:00 pm and closes Thursday, July 23, 2026 at 7:30 pm.
Wednesday, July 22, 2026
Capital Plan Hearing
Hearing time: 6:00PM – 7:30PM
CPS staff, families, and community members are invited to attend this virtual hearing regarding the District's 2027 fiscal year Capital Plan.
Where: Members of the public can view this hearing via our YouTube channel during the time listed above at youtube.com/chipubschools
Advanced online registration to speak opens Wednesday, July 15, 2026 at 5:00 pm and will close on Friday, July 17, 2026 at 5:00 pm or after all 30 speaking slots are filled.
Advance registration during this period is available by the following methods:
• Online: Registration Form (recommended)
• Phone: 773-553-1190
Members of the public may submit written comments related to the FY27 Proposed Capital Plan via the form below. The public comment form will remain open from Wednesday, July 15, 2026 at 5:00 pm and closes Thursday, July 23, 2026 at 7:30 pm.
Thursday, July 23, 2026
Capital Plan Hearing
Hearing time: 3:00PM – 4:30PM
CPS staff, families, and community members are invited to attend this virtual hearing regarding the District's 2027 fiscal year Capital Plan.
Where: Members of the public can view this hearing via our YouTube channel during the time listed above at youtube.com/chipubschools
Advanced online registration to speak opens Wednesday, July 15, 2026 at 5:00 pm and will close on Friday, July 17, 2026 at 5:00 pm or after all 30 speaking slots are filled.
Advance registration during this period is available by the following methods:
• Online: Registration Form (recommended)
• Phone: 773-553-1190
Members of the public may submit written comments related to the FY27 Proposed Capital Plan via the form below. The public comment form will remain open from Wednesday, July 15, 2026 at 5:00 pm and closes Thursday, July 23, 2026 at 7:30 pm.